FICTIONAL DOCUMENT FOR PRACTICE - no reference to real people, companies or records Office move (fictional). Tasks, duration in working days, and what each one depends on: T1 Inventory of furniture and equipment - 3 days - no dependency T2 Collecting quotes from removal firms - 5 days - after T1 T3 Choosing the removal firm and signing the contract - 2 days - after T2 T4 Desk plan for the new premises - 4 days - no dependency T5 Cabling the new premises - 6 days - after T4 T6 Message to colleagues with the date and instructions - 1 day - after T3 and T4 T7 The move - 2 days - after T3, T5 and T6 The team can work on several tasks in parallel.